Case Study
Yates / ServerFarm, Data Centers, Clarksville, AR
Electrical, safety and completions management on a project scaling to 200 personnel.

Overview
Sitewide commenced work on ServerFarm's Clarksville campus in April 2026 alongside Yates, Nabholz and NABCO. The assignment centers on electrical execution, safety and completions management as the project scales through 2026. Sitewide opened a Clarksville office to support it.
Scope of work
- Electrical execution
- Safety management
- Completions management
Results
17,247
Hours worked
100, scaling to 200
Personnel on site
0
OSHA recordables